Limerick Township has several data center proposals working through public hearings, and more dates are on the calendar: continuation hearings on November 24, December 8 and December 22, 2026 for the largest plan, and a January 12, 2027 hearing for a second plan in Linfield. No data center has been approved yet. The hearings are held at the Limerick Township Building, and the township posts every application and plan online.
This is a big topic in Limerick, Royersford and the Pottsgrove side of Route 422, and I get asked about it. So here's a plain, no spin guide to what's proposed and when the public meetings are. I'm not taking sides here. I just want you to know where to look.
What data centers are proposed in Limerick Township?
According to the township's Conditional Use Hearings page, checked November 6, 2026, there are four applications:
| Application | Applicant | Where | What's proposed | Status |
|---|---|---|---|---|
| CU 25-04 | MCD 7 LLC | About 191 acres between the Philadelphia Premium Outlets and the Limerick Clean Energy Center (Sanatoga Rd., Evergreen Rd., Zara Dr. and Possum Hollow Rd. parcels) | Eight two story data center buildings totaling just under 2.8 million square feet, plus three substations and support buildings | Hearing continuing |
| CU 26-03 | Limerick Town Center LLC | 1301 Main Street and an adjacent parcel in Linfield, on the former distillery sites | Eight two story buildings totaling just under 1.8 million square feet, about 65 feet tall | Planning Commission Dec. 10, hearing Jan. 12, 2027 |
| CU 26-05 | MCD 7, LLC | About 22 acres of the same Sanatoga Rd. and Evergreen Rd. area | One building of about 300,000 square feet (Phase 1) | Pending, no date listed |
| CU 26-06 | MCD 7, LLC | The same roughly 191 acre area | Seven more buildings (Phase 2) | Pending, no date listed |
When are the next hearings?
| Date | What | Time |
|---|---|---|
| Tue., Nov. 24, 2026 | MCD 7 hearing continues (CU 25-04) | Check the township page (recent sessions started at 6:30 p.m.) |
| Tue., Dec. 8, 2026 | MCD 7 hearing continues (CU 25-04) | Check the township page |
| Thu., Dec. 10, 2026 | Limerick Town Center plan at the Planning Commission (CU 26-03) | 7 p.m. |
| Tue., Dec. 22, 2026 | MCD 7 hearing continues (CU 25-04) | Check the township page |
| Tue., Jan. 12, 2027 | Limerick Town Center hearing (CU 26-03) | 6:30 p.m. |
The township moved all data center hearings to the Limerick Township Building at 646 West Ridge Pike and said it would use increased security measures. Dates can shift, so check the township page the week of any meeting.
What is a conditional use hearing, anyway?
It's a formal hearing in front of the Board of Supervisors where an applicant has to show a project meets the specific conditions in the township's zoning rules. Nearby residents and groups can ask for party status to take part. It's more like a court proceeding than a town hall, which is why these hearings stretch over many sessions. Spring-Ford Press's July coverage is a good look at how a session runs.
What happens after the hearings?
A conditional use decision isn't the finish line. According to WFMZ's May report, Township Manager Daniel Kerr said an approved project would still face more land use review and would need environmental approval from the Pennsylvania DEP. The township's news page also says the Board of Supervisors is looking at amendments to the industrial standards in its data center ordinance.
What does this mean if you own a home or are buying in Limerick?
If you live near Sanatoga Road, Evergreen Road, Possum Hollow Road or Main Street in Linfield, or you're shopping for a home in that area, it's worth reading the plans for yourself and putting the hearing dates on your calendar. I always tell buyers to look at what's planned around a property, not just the property itself. Township planning pages are public, and I'm happy to help you find what's proposed near any address you're considering. My Towns and School Districts page has the basics on Limerick and the Spring-Ford Area School District, and you can search homes anywhere in the area.
Frequently Asked Questions
Where are the data centers proposed in Limerick?
One plan, from MCD 7 LLC, covers about 191 acres between the Philadelphia Premium Outlets and the Limerick Clean Energy Center. Another, from Limerick Town Center LLC, is on the former distillery sites at 1301 Main Street in Linfield.
When is the next Limerick data center hearing?
The township lists continuation dates for the MCD 7 hearing on November 24, December 8 and December 22, 2026. The Linfield plan goes to the Planning Commission on December 10, 2026 and has a hearing set for January 12, 2027.
Where are the Limerick data center hearings held?
The township holds all data center conditional use hearings at the Limerick Township Building, 646 West Ridge Pike. The township has said security measures will be in place.
Has Limerick approved a data center?
No. As of November 6, 2026, the township lists the hearings as scheduled or pending. Even after a conditional use decision, a project would still need land development review and state environmental approvals.
Where can I read the data center plans for Limerick?
Limerick Township posts the applications, plans and hearing dates on its Conditional Use Hearings page. The township's data center ordinance is posted there too.
Have questions about buying or selling in Limerick?
Whether you're in Limerick, Royersford or anywhere along 422, I'm glad to talk through what's happening near you. Call or text me at 717-305-0571.
Application details and hearing dates come from Limerick Township's Conditional Use Hearings page and news notices, checked November 6, 2026. Background comes from Spring-Ford Press (July 22, 2026) and WFMZ-TV 69 News (May 11, 2026). Hearing dates can change; please confirm with the township before attending.